Calculations
Data
For the calculation of the embodied energy each slab is divided into the different materials and the volume of each material is calculated based on the entire height.
With the approximate embodied energy of each material the total embodied energy is calculated. The embodied energy for each slab is given in MJ per square meter and total height of the slab. An overview of the different materials is given in the following table.
Material |
Density |
MJ/m3 |
Assumption |
Source embodied energy |
---|---|---|---|---|
Reinforced concrete |
25 kN/m3 |
|||
Standard concrete |
24kN/m3 |
2600 |
1 and 2 |
|
High strength concrete |
24kN/m3 |
3300 |
2 and 3 |
|
Reinforcement |
78.5kN/m3 |
170000 |
Average of typical steel (about 42% recycled) |
1 and 2 |
Structural steel |
78.5kN/m3 |
170000 |
Average of typical steel (about 42% recycled) |
1 and 2 |
Timber |
3.8kN/m3 |
1300 |
Air dried |
1 and 2 |
The density values are taken form the Swiss Code SIA 261. Detail to the sources from the emodied energy can be found here.
Calculation for each Slab
Content
Flat Slab
Ribbed Slab
Waffle Slab
Hollow Core
Composite Solid Prestressed Soffit Slab
Composite Lattice Prestressed Soffit Slab
Precast Double-Tees
Steel-Concrete Composite Slab
Timber-Concrete Composite Slab
Holedeck
Slim-Floor
Voided Biaxial Slab
Laminated Timber Slab
Flat Slab
Weight: 25 kN/m3 (kN per square meter and total height of slab)
The density of reinforced concrete is taken from the Swiss Code SIA 261.
Embodied energy: 5948 MJ/m3.
Volume of materials:
Standard Concrete: 98 %vol
High strength concrete: 0 %vol
Reinforcement: 2 %vol
Steel: 0 % vol
Timber: 0 %vol
Air:0 %vol
Assumptions:
For the amount of reinforcement an example with a slab thickness of 20cm and the size 1m2 is calulated. The reinforcement in the top two layers is assumed
to be D10/150 (A=523mm2) and in the bottom layers D14/100 (A=1’540mm2).
Therefore, the volume of concrete is 0.2m3 and the reinforcment 0.004126m3 ((2*1540 + 2*523)/1000^2). Therefore, about 2% of the volume is reinforcement.
Ribbed Slab
Weight: 8.5 kN/m3 (kN per m2 and total height of slab)
To calclate the weight two typical examples are chosen. For those examples the area of reinforced concrete is calculated and divided by the total area.
Example 1:
Area concrete: Ac = 0.114m2
Total area: A = 0.7m * 0.5m = 0.35m2
-> 0.114/0.35 * 25 kN/m3 = 8.1 kN/m3
Reference: http://www.koumoulos.com/managed_images/flyer/4b.png
Example 2:
Area concrete: Ac= 0.75*0.07 + 0.15*0.28 = 0.0945m2
Total area: A = 0.75m * 0.35m = 0.2625m2
-> 0.0945/0.2625 * 25 kN/m3 = 9.0 kN/m3
Reference: https://www.youtube.com/watch?app=desktop&v=WD6wYBniEeM
Embodied energy: 2056 MJ/m3.
Volume of materials:
Standard Concrete: 33.3 %vol
High strength concrete: 0 %vol
Reinforcement: 0.7 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 66 %vol
Assumptions:
8.5kN/m3 / 25.0 kN/m3 = 0.34
34% of the total volume is reinforced concrete and the rest air. 2% out of those 34% is reinforcement (0.7%) and the rest standard concrete.
Waffle Slab
Weight: 11.2 kN/m3 (kN per m2 and total height of slab)
For the weight calculation of the waffle slab it is assumed that the ribbes have the same spacing in both direction. Then, the weight for the squared influence area which goes from the middle of the rib to the middle of the next rib is calculated.
Influence area: Ainfl = 0.75*0.75=0.5625m2
Reinforced concrete volume: Vconc= 0.6*0.6*0.07 + (0.15/2)*0.28*(0.75*4) = 0.0882m3
Therefore the weight is: Vonc*25kN/m3 / (Ainfl*h) = 0.0882m3*25kN/m3 / (0.5625m2*0.35m) = 11.2 kN/m3
Reference: https://www.youtube.com/watch?app=desktop&v=WD6wYBniEeM
Embodied energy: 2677 MJ/m3.
Volume of materials:
Standard Concrete: 44.1 %vol
High strength concrete: 0 %vol
Reinforcement: 0.9 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 55 %vol
Assumptions:
11.2kN/m3 / 25.0 kN/m3 = 0.45
45% of volume is reinforced concrete and the rest air. 2% out of those 45% is reinforcement (0.9%) and the rest standard concrete.
Hollow Core
An averaged value of the following examples is used.
16.5kN/m3 (h=0.15m), 15.5kN/m3 (h=0.20m),13.7kN/m3 (h=0.26m). (https://www.bison.co.uk/products/hollowcore-floors/)
16kN/m3 (h=0.15m), 14.5kN/m3 (h=0.20m), 13.2kN/m3 (h=0.30m), 12.5kN/m3 (h=0.40m). (https://www.mannokbuild.com/precast/hollowcore-flooring/)
Embodied energy: 3164 MJ/m3.
Volume of materials:
Standard Concrete: 0 %vol
High strength concrete: 57.25 %vol
Reinforcement: 0.75%vol
Steel: 0 % vol
Timber: 0 %vol
Air: 42 %vol
Assumptions:
14.5kN/m3 / 25.0 kN/m3 = 0.58
58% of volume is prestressed high strength concrete and prestressing strands. 0.75% of the total volume is assumed to be prestressing strands. This based on an average of the following references:
Half the amount strands needed as reinforcement in a flat slab (2%). => 1% (http://www.sustainableprecast.ca/en/precast_sustainability/material_selection/
7 strands with d=15mm, total area hollow core 1.2m*0.22m=0.264m2 => 0.001237/0.264 = 0.47% (https://www.researchgate.net/publication/320660266_Numerical_Investigation_on_Detection_of_Prestress_Losses_in_a_Prestressed_Concrete_Slab_by_Modal_Analysis/figures?lo=1)
14 strands with d=15mm, total area hollow core 1.2m*0.27m=0.324m2 => 0.002474/0.264 = 0.76% (https://www.bft-international.com/en/artikel/artikel_en_864867.html)
Composite Solid Prestressed Soffit Slab
The producer specifies a density of 24kN/m3. (https://www.precastfloors.info/Precast/media/BPMediaLibrary/Publications/Solid-Prestressed-Composite-Floors_1.pdf?ext=.pdf)
Embodied energy: 6634 MJ/m3.
Volume of materials:
Standard Concrete: 0 %vol
High strength concrete: 98 %vol
Reinforcement: 2 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 0 %vol
Assumptions:
A reinforcement ratio of 2% is assumed.
Composite Lattice Prestressed Soffit Slab
The same weight as for standard reinforced concrete is assumed because there is also a cast in place concrete layer on top of the prefab slab.
Embodied energy: 6291 MJ/m3.
Volume of materials:
Standard Concrete: 49 %vol
High strength concrete: 49 %vol
Reinforcement: 2 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 0 %vol
Assumptions:
Thickness of precast section 100 mm, thickness of in situ concrete 100mm, reinforcement ratio 2%
(Goodchild, C., Webster, R., & Elliott, K. (2009). Economic Concrete Fram Elements to Eurocode 2. Camberley UK: The Concrete Centre.)
Precast Double-Tees
Average of the following two examples is taken.
Example 1:
Area concrete: Ac= 0.2561m2
Total area: A = 0.7m * 2.5m = 1.75m2
Assuming the density of reinforced concrete: 0.2561/1.75 * 25 kN/m3 = 3.7 kN/m3
Reference: https://ascelibrary.org/doi/10.1061/%28ASCE%29EM.1943-7889.0001191
Example 2:
Area concrete: Ac= 0.477m2
Total area: A = 0.83m * 3.0m = 2.49m2
Assuming the density of reinforced concrete: 0.477/2.49 * 25 kN/m3 = 4.8 kN/m3
Reference: https://teklastructures.support.tekla.com/sv/2016i/en/ext_double_tee_ridge_beam
Embodied energy: 734 MJ/m3.
Volume of materials:
Standard Concrete: 0 %vol
High strength concrete: 16.3 %vol
Reinforcement: 0.1 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 83.6 %vol
Assumptions:
4.1kN/m3 / 25kN/m3 = 0.164
16.4% High strenght concrete Reinforced
There are 24 strands with an area of 52mm2 each.
Ratio of total volume: (24*52/1000^2)/(0.7*2.5)=0.00071 which is about 0.1%
Reference: https://ascelibrary.org/doi/10.1061/%28ASCE%29EM.1943-7889.0001191
Steel-Concrete Composite Slab
Average value from the following two examples is taken (8.4kN/m3) and then reduced due to the shape of the decking. The decking might decrease the weight of the concrete by 29%, however, not all deckings reduce the weight that much and therfore, a reduction to 7.5kN/m3 is chosen.
Steel decking has a thickness of 1mm. (https://www.montana-ag.ch/dokumente/produkte/holorib/detailprospekt/holorib_de.pdf)
Example 1: 8.3 kN/m3
Steel decking: 1/540 *78.5kN/m3=0.14 kN/m3
Concrete: 0.15/0.54*24kN/m3 = 6.67 kN/m3
Reinforcement: 0.02*(0.15/0.54) *78.5kN/m3=0.44 kN/m3
Steel profile: 0.0159m2/m *1m / (0.54*2.12) *78.5kN/m3=1.09kN/m3”
Reference: Lecture Stahlbau III ETH Zurich
Example 2: 8.5 kN/m3
Steel decking: 1/350 *78.5kN/m3=0.22 kN/m3
Concrete: 0.1/0.35*24kN/m3 = 6.86 kN/m3
Reinforcement: 0.02*(0.1/0.35) *78.5kN/m3=0.45 kN/m3
Steel profile: 0.00414m2/m *1m / (0.35*1) *78.5kN/m3=0.93kN/m3
Reference: https://www.researchgate.net/publication/228649428
Example 3: Reduction of weight due to decking
Total area: 0.150m*1.2m= 0.18m2
Area reduction due to decking: (0.18m2 - 0.127m2)/0.18m2 = 29%
The concrete weight can be reduced up to 29% or 2kN/m3 (0.29*6.8kN/m3).
Embodied energy: 4400 MJ/m3.
Volume of materials:
Standard Concrete: 28 %vol
High strength concrete: 0 %vol
Reinforcement: 0.56 %vol
Steel: 1.6 % vol
Timber: 0 %vol
Air: 69.84 %vol
Assumptions:
Steel decking: 1/540 =0.2 %vol
Concrete: 0.15/0.54 = 28 %vol
Reinforcement: 0.02*28 %vol= 0.56 %vol
Steel profile: 0.0159m2/m *1m / (0.54*2.12) = 1.4 %vol
Reference: Lecture Stahlbau III ETH Zurich
Timber-Concrete Composite Slab
Average value from the following three examples is taken.
Example 1: 6.8 kN/m3
Timber weight per meter: (0.7m*0.02m + 0.24m*0.18m)*3.8kN/m3 = 0.2174 kN/m
Concrete weight per meter: 0.7m*0.08m*25kN/m3 = 1.4 kN/m
Total weight: (0.2174kN/m + 1.4kN/m)/(0.7m*0.34m) = 6.8kN/m3
(0.7m*0.08m*25kN/m3 + )/(0.7m*0.34m) = 6.8kN/m3
Reference: Lecture Holzbau I/II ETH Zurich
Example 2: 3.6 kN/m3
Timber weight per meter: (1.1m*0.02m+ 0.26m*0.08m)*3.8kN/m3 = 0.16 kN/m
Concrete weight per meter: 1.1m*0.04m*25kN/m3 = 1.1 kN/m
Total weight: (0.16kN/m + 1.1kN/m) / (1.1m*0.32m) = 3.6 kN/m3
Reference: https://www.sciencedirect.com/science/article/pii/S0263822317317397
Example 3: 10.5 kN/m3
Timber weight per meter: (0.02m*1m + 0.16m*0.22m)*3.8kN/m3 = 0.21 kN/m
Concrete weight per meter: 0.16m*1m*25kN/m3 = 4.0 kN/m
Total weight: (0.21kN/m + 4.0kN/m) / (1m*0.4m) = 10.5 kN/m3
Reference: https://www.bauwion.de/wissen/rohbau/geschossdecke/114-holz-beton-verbunddecken
Embodied energy: 1127 MJ/m3.
Volume of materials:
Standard Concrete: 23.5 %vol
High strength concrete: 0 %vol
Reinforcement: 0.12 %vol
Steel: 0 % vol
Timber: 24 %vol
Air: 52.38 %vol
Assumptions:
Timber: (0.18m*0.24m + 0.02m*0.7m)/(0.7m*0.34m) = 24.0 %vol
Concrete: (0.7m*0.08m)/(0.7m*0.34m)= 23.5 %vol
Reinforcement: Assume 0.5% of concrete volume = 0.12 %vol
Reference: Lecture Holzbau I/II ETH Zurich
Holedeck
Average value from the following examples is taken.
htot=50 cm (ink. 5cm topping), width bottom 150mm and 200mm
6.0 kN/m3 (average of those two widths)
htot=35 cm (ink. 5cm topping), width bottom 150mm and 200mm
3.8 kN/m3 (average of those two widths)
Embodied energy: 1041 MJ/m3.
Volume of materials:
Standard Concrete: 19.6 %vol
High strength concrete: 0 %vol
Reinforcement: 0.4 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 83.6 %vol
Assumptions:
5kN/m3 / 25kN/m3 = 0.20
20% of volume is reinforced concrete.
Slim-Floor
The weight of reinforced concrete (25kN/m3) is reduced to 18kN/m3 due to the decking which reduces the weight up to 29%.
0.150m*1.2m= 0.18m2
(0.18m2 - 0.127m2)/0.18m2 = 29%
Embodied energy: 5948 MJ/m3.
- Volume of materials:
Standard Concrete: 98 %vol
High strength concrete: 0 %vol
Reinforcement: 1.3 %vol
Steel: 0.7 % vol
Timber: 0 %vol
Air: 0 %vol
Assumptions:
The steel decking is about 1mm thick which is about 0.7% of the volume (1/150). The total amount of reinforcement and steel decking is assumed to be 2%. Therefore, the reinforcement itself is 1.3% vol.
(https://www.montana-ag.ch/dokumente/produkte/holorib/detailprospekt/holorib_de.pdf)
Voided Biaxial Slab
The weight of reinforced concrete (25kN/m3) is reduced to 18kN/m3 due to the voided elements.
Reference:
18 kN/m3 (h=50cm). (https://www.cobiax.com/ch/de/produkte/)
17.5 kN/m3 (reduction by about 30%). (https://www.voidedconcrete.com/system)
Embodied energy: 4200 MJ/m3.
- Volume of materials:
Standard Concrete: 70 %vol
High strength concrete: 0 %vol
Reinforcement: 1.4 %vol
Steel: 0 % vol
Timber: 0 %vol
Air: 28.6 %vol
Assumptions:
About 30% reduction of concrete and reinforcement due to voided elements.
Laminated Timber Slab
Reference:
3.8 kN/m3 (https://wissenwiki.de/Brettschichtholz)
3.85 kN/m3 (https://www.binderholz.com/fileadmin/user_upload/pdf/produkte/brettschichtholz-kvh.pdf)
3.8 kN/m3 (Swiss Code SIA 265)
Embodied energy: 1300 MJ/m3.
Volume of materials:
Standard Concrete: 0 %vol
High strength concrete: 0 %vol
Reinforcement: 0 %vol
Steel: 0 % vol
Timber: 100 %vol
Air: 0 %vol
Assumptions:
100% of this slab is timber.
References
Source 1: Ashby, M. (2013). Materials and the Environment. Oxford UK: Elsevier.
Source 2: Hammond, G.P. and C.I. Jones (2008), Embodied energy and carbon in construction material. Bath UK: Proc. Instn Civil. Engrs:Energy.
Source 3: Alcorn, A. (2001). Embodied Energy and CO2 Coefficents for NZ Building Materials. Wellington NZ.