Steel-Concrete Composite Slab

_images/stahl_beton.jpg

Description

Steel-concrete composite slab consist of steel profiles, usually and I- or H-profiles, steel decking acting a lost formwork and cast in situ reinforced concrete on top. The concrete quality is usually around C30/37, but it can go from C20/25 up to C50/60. The concrete is connected to the steel beams using shear studs. The steel decking is oriented perpendicular to the steel beams so the force can be introduced better into the steel and so the decking can stand without support during construction. For that the steel beams need to be about 3 to 4 m apart from each other. The economical span lays between 4 and 10 m, which is the typical span in European office buildings, this is also where they are typically used. Steel-concrete composite slab can be easily made continuous by putting more rebars in the concrete above the beam to increase the resistance against negative moments.

Steel-concrete composite slabs do not perform well during fires, because the steel beams lose their loading capacity fast without protection. Usually, 60 minutes can be achieved without much effort.

The flexibility on site is average due to cast in situ concrete and all the components being installed after each other. This leaves options for spontaneous adaptation. The flexibility in geometry is rather bad due to the steel decking dictating the direction of the force flow, thus not allowing for openings. Building systems cannot be integrated into the slab but can be put between the steel beams, all the necessary cables and tubes are not blocked by the steel beams, because it is statically no problem to put holes in the webs of the steel beams. The complexity in fabrication and installation is also average which is quite good for a non-prefab slab, but that is mainly because the steel profiles are prefabricated, the steel decking acting as lost formwork also helps. All the connections to the beams and columns can be made in steel which is also a plus. The construction time is average because the steel profiles and the decking are quickly installed, however, the concrete takes some time to cure. This can slow down construction heavily, especially if one decides to prop up the steel profiles to decrease the stress in them.

The concrete layer is usually thick enough that vibration is not a problem.
The slenderness typically lays around l/h=20, which is on the low end. But the ability to put building systems between the steel profiles make steel-concrete composite slabs highly competitive in office buildings, where lots of building systems are required and high building speed is required.

Database

Floor type

Steel-Concrete Composite Slab

Materials

concrete (from C20/25 to C50/60 possible)_structural steel_reinforcing steel_steel decking

Description

steel beam carrying steeldecking that acts as lost formwork for in sito concrete slab above

Way of carrying

Does the main span carry in one or two directions?

one way slab

Span width low [m]

Economically possible

4

Span width high [m]

Economically possible

10

Additional measures when installing

decking_shear stud_maybe propping

Prefab?

Is prefab possible?

yes/no

Continous slab?

Can you build the slab with supports in middle of the slab?

yes

Building systems integratable?

Can buildings systems be included into the slab itself?

yes

Fire

Fireresistance without costly measures [min]

60

Substructure

Certain prerequisites necessary?

no

Prone to vibration

no

Environment

General classification including formwork

1 to 5 terrible to very good

2

Construction time

Time on site

1 to 5 very slow to very fast

3

Flexibility

Average of the next two

1 to 5

2.5

Flexibility on site

How flexible is the system to spontaneous changes on site?

1 to 5 terrible to very good

3

Flexibility geometry

How good can you adapt the slab to complex geometries?

1 to 5 not at all to very easy

2

Complexity

Average of the next two

1 to 5

3

Complexity fabrication

Complexity of floor itself.

1 to 5 very complicated to very simple

3

Complexity installation

Complexity installation on site

1 to 5 very complicated to very simple

3

Slenderness l/h 3kPa

Applied load (without selfweight)

Residential building

20

Slenderness l/h 4kPa

Applied load (without selfweight)

Office building

20

Weight [kN/m3]

per m2 and total height of slab

7.5

Embodied energy [MJ/m3]

per m2 and total height of slab

4400

References

General information:

Lecture Stahlbau III. ETH Zürich.

Span width:

3 - 8m (https://constructalia.arcelormittal.com/files/AMC_floors_guide_EN_June2019_LR–b47b21285b39514432cf4da5d75b23f1.PDF)
6 - 12m (https://www.szs.ch/wp-content/uploads/2017/08/2014-01-02_02_d_Stahldeckensysteme.pdf)

Fire resistance:

30min without additional measures, 60min with some measures (https://www.sciencedirect.com/science/article/abs/pii/0143974X9400015A#:~:text=During%20fire%20the%20sheeting%20heats,is%20at%20least%2030%20minutes.)
30min with concrete thickness up to 6cm, 60min if thicker (https://www.steelconstruction.info/Design_of_composite_steel_deck_floors_for_fire)

Slenderness:

l/h=19 for 3kPa, l/h=19 for 4kPa (Lecture Stahlbau III ETH Zurich)

Weight:

Calculations

Embodied energy:

Calculations

Photo Source:

https://www.rudolf-hensel.de/produkte/hensotherm-820-ks-brandschutz-fuer-beton/